Harris County Airport Plans to Double Its 1,500-Square-Foot Terminal on a $750,000 Cap and Approves $241,600 in Design Work
An Eastern Air Express Boeing 737 about to land on Runway 24 at Columbus Airport. Photo: Mccunicano / Wikimedia Commons (CC BY-SA 4.0)
HAMILTON, Ga. - Harris County is moving ahead with a plan to double the size of the roughly 1,500-square-foot terminal at its airport in Pine Mountain, with funding for the work capped at $750,000, according to minutes of the county commission's Oct. 20 meeting. The same night, commissioners approved $241,600 in engineering task orders for the terminal, a runway overlay and a site for new T-hangars, plus a five-year capital plan for the airport that runs through fiscal 2032. The county broke ground on the terminal expansion during its Oct. 24 airport open house, which drew an estimated 3,000 people, according to the Nov. 3 minutes.
The work is part of a broader push at the county-owned general aviation airport at 789 Sky Meadow Drive, which serves business and recreational pilots. The plans also address hangar space and the condition of the runway and other paved surfaces. A construction contract for the terminal has not been awarded, and no completion date has been set.
State money for the terminal
Commissioners approved a contract with the Georgia Department of Transportation for the terminal project at their May 20, 2025, meeting. According to those minutes, the estimated cost was $733,333.33, with $550,000 from the state's Georgia Airport Aid program and $183,333.33 from the county. A groundbreaking planned for the May 17, 2025, open house was canceled because of weather, the minutes say.
The county's proposed fiscal 2026 budget then set aside $750,000 for the terminal expansion and $1,615,000 for hangar site preparation, a combined $2,365,000. The budget said the county would receive $2,096,750 in reimbursement from the FAA and GDOT if those projects were approved. It described the airport as a 235-acre field with a 5,001-foot runway, 29 T-hangars, 65 tie-down spots and two 10,000-square-foot corporate hangars.
What the terminal expansion includes
The agenda summary for the Oct. 20 meeting says the existing building "lacks the space needed to suitably accommodate visitors." The expansion is meant to double its size, upgrade the roof and windows, meet ADA standards and add a conference room for county and airport meetings that pilots and passengers can also use as a workspace, according to the minutes and the summary. Funding for the terminal work is capped at $750,000, and the bid would include alternates, such as landscaping, that the board could choose to add after bids come in.
Lead Edge Design Group, the county's airport consultant, will handle design and bidding under Task Order 11. The task order sets a fee of $75,500 for design and $8,500 for the bid phase, or $84,000. It calls for design documents to be finished within 60 days of the county's approval.
Runway overlay
Task Orders 8 and 9 cover an overlay of Runway 9-27, described in the agenda summary as 5,002 feet long and 100 feet wide, plus new pavement markings. The summary says GDOT's 2025 pavement management plan rated the runway 61 out of 100 and that scores under 70 call for repaving. It says the pavement is nearing the end of its 20-year life.
Task Order 8 pays $80,000 for preliminary design and $16,500 for a topographic survey, a total of $96,500. Task Order 9 adds $8,500 for the bid phase. Those are engineering fees, not the cost of repaving the runway.
More hangar space
All existing hangars at the airport are full and there is a waiting list, according to the agenda summary. Task Order 10 covers final design and bidding for site preparation and paving for two 10-unit T-hangar buildings west of the existing hangars, including an access road, car parking and a connector to the taxiway. Its fees are $44,100 for final design and $8,500 for the bid phase.
The summary says GDOT is expected to pay 75% of the site work, with the county paying 25%. Building the hangars themselves would be a separate project, decided after weighing hangar income against cost. No schedule or rental rates for new hangars have been set.
Five-year airport plan
Every Georgia airport must send GDOT a five-year capital improvement plan each November to stay eligible for funding, consultants Phil Eberly and Amanda Rostin of Lead Edge told the board, according to the minutes. They said the Harris County Airport ranks 40th of 103 Georgia airports for based aircraft. They also said the board is under no obligation to spend the money and can change the plan at any time. The plan attached to the agenda lists these projects and estimated costs:
| Fiscal year | Project | Estimated cost |
|---|---|---|
| 2028 | Parking lot expansion; DBE plan update | $176,667 |
| 2029 | Land acquisition and obstruction removal; terminal apron rehabilitation | $666,667 |
| 2030 | New hangar area site preparation and paving | $1,500,000 |
| 2031 | Parallel taxiway rehabilitation | $1,200,000 |
| 2032 | Hangar access road extension | $800,000 |
The five-year total is $4,343,334, with $3.9 million expected from federal sources, $216,666 from the state and $226,668 from the county, according to the plan. Commissioner Rob Grant moved to approve the plan and the task orders, and Commissioner Greg Gantt seconded both motions. Both passed unanimously with Commissioner Bobby Irions absent.
What happens next
The task orders give Lead Edge 60 days to complete design documents for the terminal and the hangar site, and preliminary design for the runway. The firm will then distribute bid documents, hold the bid openings and certify the results. The county's bids and proposals page listed no airport solicitation as of Nov. 24.
The commission has not voted on an airport item since Oct. 20, according to its Nov. 3 minutes and Nov. 17 action agenda. The construction price for the terminal will not be known until bids are opened. The board will then decide which alternates, if any, to add within the $750,000 cap.
Source: Harris County BOC minutes (Oct. 20, Nov. 3, 2026) and Oct. 20 agenda packet; FY2026 budget; BOC minutes (May 20, 2025)
News organizations may republish this story with credit. See our guidelines.
Know someone who'd want to read this? Email it to a friend.
Plan your weekend with Columbus Times
Get This Weekend in Columbus every Thursday: the best local events, free things to do and family fun, plus each evening's local news. Free, and you can unsubscribe anytime.
By signing up you agree to get the Columbus Times email newsletter. Unsubscribe anytime with one click.
Comments
Be respectful. No personal attacks, hate speech, spam or anyone's private information. Every comment is reviewed before it appears. Comment rules
No comments yet. Be the first to share your thoughts.