Last 8 Miles of the Man O' War Trail Go Out to Bid: A 10-Foot Paved Path, 180 Days to Build and a $5 Million State TIA Line
The Chipley Historical Center in Pine Mountain, with a caboose on display; Chipley is one of the trail's trailheads. Photo: Rivers Langley; SaveRivers / Wikimedia Commons (CC BY-SA 3.0)
HAMILTON, Ga. - The Man O' War Trail has been stuck at Mulberry Creek for more than three years, and Harris County has now asked contractors what it would cost to finish the job. A county advertisement for bids describes Phase VII as "roughly eight (8) miles" of 10-foot-wide asphalt path laid along an abandoned railroad bed. Sealed bids were due through QuestCDN at 10 a.m. on Tuesday, Nov. 10, and as of this week no contract had been awarded.
That would be a big jump for a trail that already welcomes cyclists, runners, dog walkers and e-bikes, according to the county's tourism site. Harris County said in August 2023 that the paved path runs 13.5 miles from the Harris-Meriwether County line in Pine Mountain south to Mulberry Creek. Another eight miles would push it to roughly 21.5 miles, and the county's own plan points that new stretch toward Columbus.
What the bid package asks for
The advertisement, posted on the county's bids page and prepared by engineering firm Carter & Sloope Inc. of Canton, spells out a fairly simple build. The contractor would grade and pave the 10-foot path, then add wooden guard railing, crosswalks, driveway replacement and signs. The ad gives the winning firm 180 consecutive calendar days to finish, which is about six months, and says the work "will be awarded in one (1) Contract."
Bidders had to post a bid bond or certified check worth at least 10% of the base bid, and the winner must carry performance and payment bonds equal to 100% of the contract price. The ad says the base cost of every bid would be posted on QuestCDN within 30 minutes of the deadline, but that site requires an account, and the county had not posted the numbers on its own site. Bids cannot be withdrawn for 60 days after the Nov. 10 opening, which keeps them binding until about Jan. 9, 2027.
The paperwork also shows how ready the project is. The ad lists a Georgia Department of Transportation permit as "Submitted," while a land disturbance permit, a stormwater permit and an Army Corps wetlands permit are all marked "Not Applicable." It says every easement and right-of-way "have been obtained or will be obtained" by the county before it issues a notice to proceed.
Where the last 8 miles go
Here is the one thing the bid ad does not say: it never names the two ends of the new section. The county has been clear about the route in the past, though. When Phase VI opened in August 2023, Harris County wrote that "the last eight miles of the trail from Mulberry Creek to the Columbus/Muscogee County line" was scheduled for 2026 or 2027.
Back in 2022, WTVM quoted then-County Manager Rand Dowling describing the same Mulberry Creek-to-Muscogee stretch as "three or four years from now." The bid ad's eight-mile length matches the county's 2023 description, but the exact start and finish points will only be confirmed by the construction plans or a county statement. Until then, readers should treat the Muscogee County line as the stated goal rather than a surveyed end point.
Who is paying
The money story has shifted a little since 2023. Back then the county said the final miles would be "funded by TSPLOST funds when they become available," but the new ad says the project is paid for by the Georgia Department of Transportation through the Transportation Investment Act of 2010. That is the regional TIA sales tax that also pays for road work across the River Valley region.
The state's annual TIA report for Nov. 22, 2024, through Nov. 21, 2025, lists "Continuation of the Man O' War Railroad Recreation Trail" as Harris County project RVRC2-07. It carries a $5 million estimated cost and showed $0 spent through that period. The bid results will show whether the real price lands above or below that figure.
How it got here
The trail follows the route of the Man O' War, a Central of Georgia Railway passenger train that started in 1947 and ran between Columbus and Atlanta, according to the Explore Harris County tourism site. The train stopped daily in Pine Mountain for more than 20 years, and the tracks were fully taken out of service in 2007. Today the path has mile markers, kiosks and trailheads from Chipley and downtown Pine Mountain down through Hamilton.
Phase VI, the last piece to open, gives a sense of scale. Commissioners hired Robinson Paving of Columbus in February 2023 on a low bid of $1,166,189.30, the lowest of four, to pave 3.15 miles from just south of Hamilton to near Mulberry Creek. The county later put the finished cost at $1.14 million and held a ribbon cutting on Sept. 19, 2023.
What happens next
At the Sept. 15, 2026, commission meeting, County Clerk Andrea Dzioba reported that the trail project was waiting on GDOT sign-off on plans before advertising could begin. The bids went out after that, and the next step is a contract award by the Board of Commissioners. The Nov. 17 action agenda did not include the trail, and the county's bids page still showed a blank "Awarded" column for the solicitation this week.
The board meets in Room 215 of the Harris County Courthouse at 102 N. College St. in Hamilton. With bids binding into early January and a 180-day construction clock in the ad, the earliest finish would come about six months after the county gives the go-ahead. Trail users who want to follow along can watch the commission's posted agendas for a Man O' War Trail contract item.
Source: Harris County bid ad (Oct. 2026); Harris County BOC (Sept. 15 & Nov. 17, 2026); Harris County (Aug. 21, 2023); GDOT TIA report (2025)
News organizations may republish this story with credit. See our guidelines.
Know someone who'd want to read this? Email it to a friend.
Plan your weekend with Columbus Times
Get This Weekend in Columbus every Thursday: the best local events, free things to do and family fun, plus each evening's local news. Free, and you can unsubscribe anytime.
By signing up you agree to get the Columbus Times email newsletter. Unsubscribe anytime with one click.
Comments
Be respectful. No personal attacks, hate speech, spam or anyone's private information. Every comment is reviewed before it appears. Comment rules
No comments yet. Be the first to share your thoughts.