$2.43 Million Contract Would Add Nearly a Mile of Dragonfly Trail on River Road, Linking Cascade Road to the Riverwalk With a Footbridge

A rendering of the planned Dragonfly Trail pedestrian bridge on the River Road Connector, the segment Columbus Council took up Nov. 17.

A rendering of the planned Dragonfly Trail pedestrian bridge on the River Road Connector, the segment Columbus Council took up Nov. 17. Rendering: Dragonfly Trails, Inc.

COLUMBUS, Ga. - The gap has had a name in city slideshows for more than five years: the River Road Connector. A Dragonfly Trails presentation to Columbus Council in June 2022 called it the "single most requested connection from community," and said it would connect north Columbus residents to the Mill District, Uptown, Midtown and the Fall Line Trace. On Tuesday, Nov. 17, a construction contract to build it was on council's agenda.

The city manager's purchasing agenda asked council to authorize a $2,429,900 contract with Excellere Construction LLC of Marietta for the Dragonfly Trail River Road Segment, according to the Nov. 17 agenda packet. The trail would start near Cascade Road, run south along River Road, which is State Route 219, and turn west to the existing riverwalk at Lake Oliver Road. The city had not posted summary minutes or vote results for the Nov. 17 meeting on its meeting portal when this story was written, so the outcome of the vote is not confirmed here. WTVM's Nov. 17 report on the meeting covered the stadium renovation and security vehicles for the mayor-elect and did not mention the trail contract.

What the contract would build

The project is about 5,026 linear feet, or just under a mile, of 10-foot-wide concrete trail, according to the agenda item. It includes a pedestrian bridge, landscaping, stormwater improvements and trail amenities, plus clearing, minor demolition, erosion control, grading and signage. Because parts of the route sit on state right-of-way, the city obtained an encroachment permit from the Georgia Department of Transportation, the packet says.

Advertisement

A city engineering update presented to council on Oct. 14, 2025, broke the segment down in more detail. It listed about 1,300 feet of new multi-use trail, about 3,700 feet of on-street shared-use trail and a 160-foot pedestrian bridge, with bidding then expected in February 2026. Questions answered in the bid documents also show the job includes an Eco-Counter, a device that tallies trail users, and the plans reference a bridge foundation investigation prepared by the engineering firm Terracon.

Seven bids, two thrown out

The city posted the bid on Aug. 18 on its purchasing page, the Georgia Procurement Registry and OpenBids. The original Sept. 23 due date was pushed back by addendum, and seven bids were opened on Oct. 28, according to the packet. Excellere's base bid was $2,209,000, and the contract adds a 10% contingency of $220,900.

BidderTotal with 10% contingency
Southeastern Site Development, Newnan (non-responsive)$2,151,269.01
Excellere Construction, Marietta$2,429,900.00
Hasbun Construction, Alpharetta$2,760,820.74
JHC Corporation, Jonesboro$2,762,835.90
Tri Scapes, Cumming$2,859,610.86
IP Construction, Kennesaw (non-responsive)$2,914,867.27
Strack, Fairburn$3,448,500.00

The lowest price on paper came from Southeastern Site Development of Newnan, but the city ruled that bid non-responsive because the company did not submit the most recently revised pricing page, which added line items. IP Construction of Kennesaw was also disqualified for a missing signed proposal form, a mandatory part of the bid. That left Excellere as the lowest responsive bidder, and the packet lists its planned participation by disadvantaged business enterprises at 60.44%, well above the city's 10% goal.

Who pays

The money is already set aside, according to the packet. Of the total, $2 million would come from the 2021 SPLOST, the voter-approved local sales tax, in a transportation account for trail and sidewalk improvements. The other $429,900 would come from the 2012 Transportation SPLOST, in an account named for the Lake Oliver Marina trail connection.

A connector that grew

The price is far higher than the first estimates. In July 2021, a council agenda item put the River Road connection's budget at about $850,000, with $283,000 in TSPLOST money and the rest from outside sources, and said the Friends of the Dragonfly Trails fund had paid for engineering and design. The June 2022 presentation split that $850,000 among Dragonfly Trails, Columbus Water Works and the city and described the project as "fully funded & designed; ready to bid."

The route has changed since then as well. The 2021 plan described a 0.6-mile trail from the River Road and Bradley Drive roundabout to the northern end of the RiverWalk, while the current design runs from near Cascade Road and includes the pedestrian bridge. The 2026 agenda packet does not explain how the scope and cost grew.

What is still unknown

The agenda item does not give a construction start date or a completion deadline. Neither the city nor Dragonfly Trails had announced a schedule as of this writing. Parts of the work sit in state right-of-way along River Road, but no lane closure plan has been released.

The segment also feeds a larger goal. Dragonfly Trails is the partner in charge of the Columbus Ahead regional plan's target of building a trail network of at least 61 miles, the most extensive in Georgia, the Ledger-Enquirer reported Oct. 21. Columbus Times ran the bid notice for this segment on Sept. 29, and this contract is the step that would turn that plan into concrete.

Source: Columbus Council agenda (Nov. 17, 2026); City RFB 27-0006 (Aug.-Sept. 2026); WTVM (Nov. 17, 2026); Ledger-Enquirer (Oct. 21, 2026)

Read next · Local Woman Charged in Phenix City Hit-and-Run Death of Bicyclist

News organizations may republish this story with credit. See our guidelines.

Plan your weekend with Columbus Times

Get This Weekend in Columbus every Thursday: the best local events, free things to do and family fun, plus each evening's local news. Free, and you can unsubscribe anytime.

By signing up you agree to get the Columbus Times email newsletter. Unsubscribe anytime with one click.

Own a Columbus business? 20,000+ page views in 30 days. Ads from $125/month. See ad options Follow Columbus Times on FacebookLocal news, events and people, in your feed every day. Follow

Comments

Be respectful. No personal attacks, hate speech, spam or anyone's private information. Every comment is reviewed before it appears. Comment rules

No comments yet. Be the first to share your thoughts.

Leave a comment

Replying to

Most read this week

  1. Columbus Weighs Truist Over Synovus and a Civic Center Manager
  2. Fort Benning Ceremony Calendar
  3. County Line Road Interchange Plan: Comments Due Nov. 20
  4. 4 Options for McClung Stadium, From $16 Million to $85 Million
  5. Hubert Smith III Talks Love, Dating and Life After Reality TV