A splash pad at Water Works Park in Baxley, Ga. Carver Lake Park's Phase 1 plans include improvements around the splash pad that opened at Carver Park in 2025.

A splash pad at Water Works Park in Baxley, Ga. Carver Lake Park's Phase 1 plans include improvements around the splash pad that opened at Carver Park in 2025. Photo: Michael Rivera / Wikimedia Commons (CC BY-SA 4.0)

COLUMBUS, Ga. - The city of Columbus is looking for a contractor to rebuild much of Carver Lake Park on Hunter Road, the east Columbus park where a splash pad opened in 2025. A request for bids dated Nov. 10 from the city's Purchasing Division describes "Carver Lake Park - Phase 1" as a redevelopment that includes a 10-foot-wide multi-use trail, new parking, a playground and pavilion area, and work around the existing splash pad. Contractors must attend a mandatory site visit at 11 a.m. on Monday, Nov. 30, and sealed bids are due by 2:30 p.m. on Wednesday, Dec. 16.

The city is also collecting bids to replace the roof at the Fox Senior Center on 5th Avenue. That job has its own mandatory site visit at 10:30 a.m. Thursday, Nov. 19. Both bid calls were listed as upcoming advertisements on the Columbus Council agenda for its Nov. 17 meeting.

What Phase 1 would build

The bid document, Request for Bids No. 27-0017, says the base bid covers demolition and removal of existing site improvements, clearing and grubbing, and earthwork and grading. It also calls for building and rebuilding access drives and parking areas, including accessible parking, along with asphalt pavement, permeable pavers, concrete sidewalks and curb and gutter. The list continues with pedestrian trails and crossings, park benches, fencing, signs and pavement markings, landscape islands, landscaping, and the storm drainage and utility work needed to support it.

Advertisement

The recreation pieces named in the document are "playground and pavilion areas and improvements surrounding the existing splash pad." The city says the work will be awarded as one contract based on the "Base Bid Total Phase 1." Bidders are also asked to price one alternate, which would replace an asphalt walking trail with a 4-inch concrete trail.

The bid form does not include a city cost estimate, so the price of the project will not be known until bids are opened. It does set aside a $25,000 owner allowance for materials testing. The design firm named in the advertisement is Barge Design Solutions, which lists an office at 1201 Front Ave. in Columbus.

The timeline and the rules for bidders

The contract gives the winning builder 550 consecutive calendar days to reach substantial completion and 580 days to be fully finished and ready for final payment. If the work runs late, the agreement says the contractor would pay the city $500 a day in liquidated damages for each deadline missed. The document does not give a start date, but by simple arithmetic a job that began in early 2027 would have a substantial-completion deadline in mid-2028.

Bids must be submitted online through OpenBids, the platform formerly called DemandStar, and the city will hold a virtual bid opening during the 3 p.m. hour on Dec. 16. Each bid must come with a bid bond of 5% of the bid, and the winner must post performance and payment bonds for 100% of the contract. Copies of the plan book cost $50 from Memphis Reprographics, and the Purchasing Division says it will deem "non-responsive" any bid from a contractor who was not represented at the Nov. 30 site visit.

The advertisement says bidders must show good-faith efforts toward the owner's goal that at least 10% of the bid amount go to minority-owned firms and 5% to women-owned firms. The city's purchasing section separately lists a 10% goal for disadvantaged business enterprises. The site visit will start at the Carver Park Recreation Center, 6665 Hunter Road.

A park with a hard history

Carver Park has had a rough reputation, and city leaders have tied its revival to new amenities. When the splash pad was dedicated in August 2025, District 4 Councilor Toyia Tucker told WRBL, "It's bringing more revitalization to this area," and said that "prior, Carver Park had a bad name." WRBL reported that the park had been closed on weekends after a 2021 council vote that followed two deadly shootings, and that weekend access returned with the splash pad, which was paid for with 2021 SPLOST sales tax money.

The park also runs on reduced hours. A May 18, 2026, administrative order signed by Mayor Skip Henderson cites complaints about disruptive and threatening events after dark at Carver Park and Rigdon Park. Under that order, Carver Park closes from 8 p.m. to 6 a.m. while the splash pad is open, and from 7 p.m. to 6 a.m. starting the first weekend after the splash pad closes for the season.

The order says the reduced hours stay in effect through the 2027 pool season. After that, park hours return to those set in the city code unless the city manager extends the order or council changes the ordinance. Organized activities run by the Parks and Recreation Department are exempt.

The Fox Senior Center roof

The second project, Request for Bids No. 27-0002, covers the Fox Senior Center at 3720 5th Avenue. The specifications call for a complete roof tear-off, replacement of the metal roof deck, new R-25 insulation and a cover board, and a new 60-mil TPO single-ply membrane. The job also includes repairing and recoating the building's exterior insulation and finish system walls, replacing any panels found to be water-damaged.

The project manual says tear-off noise and adhesives "shall not interfere with the use of the building," which suggests the center is expected to stay in use during the work. Bids for the roof are due at 2:30 p.m. on Dec. 9, also through OpenBids, and the city has set a 10% disadvantaged business goal. Contractors who want to bid must sign in at the center for the 10:30 a.m. site visit on Nov. 19.

Bid documents and any addenda for both projects are posted on the city's bid opportunities page at columbusga.gov. Questions go to the Purchasing Division, which lists Heather Biddle as the buyer for both projects. Residents who want to follow the contracts can watch for the award recommendations on future Columbus Council agendas.

Source: City of Columbus RFB 27-0017 (Nov. 10, 2026) and RFB 27-0002 (Nov. 3, 2026); Mayor's order (May 18, 2026); WRBL (Aug. 25, 2025)

Read next · Local Columbus Weighs Truist Over Synovus and a Civic Center Manager

News organizations may republish this story with credit. See our guidelines.

Plan your weekend with Columbus Times

Get This Weekend in Columbus every Thursday: the best local events, free things to do and family fun, plus each evening's local news. Free, and you can unsubscribe anytime.

By signing up you agree to get the Columbus Times email newsletter. Unsubscribe anytime with one click.

Own a Columbus business? 20,000+ page views in 30 days. Ads from $125/month. See ad options Follow Columbus Times on FacebookLocal news, events and people, in your feed every day. Follow

Comments

Be respectful. No personal attacks, hate speech, spam or anyone's private information. Every comment is reviewed before it appears. Comment rules

No comments yet. Be the first to share your thoughts.

Leave a comment

Replying to

Most read this week

  1. Columbus Weighs Truist Over Synovus and a Civic Center Manager
  2. County Line Road Interchange Plan: Comments Due Nov. 20
  3. Fort Benning Ceremony Calendar
  4. How to Ride METRA: $1.30 Fares, 10 Routes, Free Uptown Shuttle
  5. Columbus Bulk Trash, Limbs and Landfill Fees: What to Know