Double Churches Merger Grows to $56.85 Million: A New 2-Story Elementary School, a Shared K-8 Cafeteria and a December Vote on Borrowing

Wynnton Arts Academy, a Muscogee County School District elementary school in Columbus. It is shown as one of the district's school campuses; it is not Double Churches.

Wynnton Arts Academy, a Muscogee County School District elementary school in Columbus. It is shown as one of the district's school campuses; it is not Double Churches. Photo: Ken Owens Photography / Wikimedia Commons (CC BY-SA 3.0)

COLUMBUS, Ga. - The Muscogee County School District's plan to fold Double Churches Elementary and Double Churches Middle into one shared campus now carries an estimated maximum cost of $56.85 million, nearly double the roughly $30 million first set aside for Double Churches construction. The school board was scheduled to vote Monday, Nov. 16, at 6 p.m. on a first-phase construction budget of about $31 million, according to the Ledger-Enquirer. A second vote, on borrowing as much as $56.61 million to keep the project and other sales-tax work moving, is expected in December.

The project is paid for by the 2024 E-SPLOST, the 1-cent education sales tax Muscogee County voters extended in 2024. Chief Operations Officer Travis Anderson told the board at a work session that the elementary school was identified as the first school to replace under that referendum, WTVM reported. If the schedule holds, district spokeswoman Kimberly Wright told the Ledger-Enquirer, construction would begin in late February or early March 2027.

What would be built

The plan puts a new two-story elementary school and gym on the site of the middle school's old gym and athletic field, according to the Ledger-Enquirer's account of the Nov. 9 work session. Double Churches Middle would get minor upgrades, a new gym and a new athletic field. The two schools would share a new K-8 media center and cafeteria, each divided so elementary and middle school students use separate sides.

Advertisement

The Ledger-Enquirer reported the district's estimate in four pieces. The new elementary school is by far the biggest, at more than three of every five dollars. The table below lists each piece as the newspaper reported it.

Piece of the projectEstimated cost
New elementary school$35.8 million
Middle school gym and athletic field$6 million
Middle school renovation$1.8 million
Fees, contingency, testing, furniture, fixtures and equipment$13.25 million
Estimated maximum total$56.85 million

Phase one, the roughly $31 million piece on Monday's agenda, covers site work, the elementary school's foundation, steel and masonry. Director of Construction Jeff Battles said that phase "gets us all the way through getting the new elementary school up and dried in with a roof on it," the Ledger-Enquirer reported. Phase two, the interior finishing work, will be brought to the board later.

Why the district wants one campus

Anderson told the board the project has been in the works since November 2024, when an architect who reviewed the elementary property recommended combining it with the middle school next door. He said the elementary building's age and its heating and air-conditioning system are problems, and that the school is "undersized for that community," according to WTVM. At the middle school, he said, some athletic fields and the gymnasium do not meet current standards.

"It's a much larger project than initially established," Anderson said, according to the Ledger-Enquirer. He said the new design meets the elementary school's needs while also fixing problems at the middle school. Board Chairwoman Pat Hugley Green, who represents District 1, said the district has to deliver what it promised voters when they approved the sales tax, the newspaper reported.

The traffic problem on Whitesville and Whittlesey

Families who use the campus say afternoon pickup is already a squeeze. Anthony Burris, whose grandchild attends Double Churches Elementary, told WTVM that traffic on Whitesville and Whittlesey roads backs up after dismissal and that it can take "5-10 minutes just to get into your own neighborhood." Anderson said the combined campus would add room for car stacking, and that the back area, a bus loop, could be used for that.

How the money works

Muscogee's E-SPLOST was extended for five years or until $290 million is collected, whichever comes first, and voters authorized up to $90 million in debt, according to the Ledger-Enquirer. The tax brings in about $4.2 million a month, or roughly $90 million over 21 months, and investment earnings have added another $2.4 million, for a total of $92.4 million. About $34 million had been spent as of Oct. 31, about $24 million is budgeted for other projects and about $33 million is still available to assign.

That gap between what the project costs and what is in the bank today is why the district wants to borrow. Chief Financial Officer Janice Bloodworth told the board that "without these funds, many of the projects would have to be delayed," and said the financing would keep construction bills paid as they come due. The district has used debt for past E-SPLOST projects, and the exact amount to borrow is expected to be set within about a month, the newspaper reported.

What is still unknown

The news reports on the work session did not give current enrollment at either school or the planned student capacity of the new building. They also did not say whether any classes would move during construction, although the new elementary school is planned for land now used by the middle school's old gym and field rather than the current elementary building. The result of Monday's phase-one vote was not available from the district or local news outlets when this story was prepared; parents can check the board's posted actions on the district's BoardDocs site.

The next public checkpoint is the board's December vote on the financing. That vote will decide how much the district borrows against future sales-tax collections to cover Double Churches and other E-SPLOST projects. Construction crews would not be on site until late winter at the earliest, under the timeline the district gave the Ledger-Enquirer.

Source: Ledger-Enquirer (Nov. 12, 2026); WTVM (Nov. 13, 2026)

Read next · Education Fort Benning Families: 8 School Transfer Rules to Know

News organizations may republish this story with credit. See our guidelines.

Plan your weekend with Columbus Times

Get This Weekend in Columbus every Thursday: the best local events, free things to do and family fun, plus each evening's local news. Free, and you can unsubscribe anytime.

By signing up you agree to get the Columbus Times email newsletter. Unsubscribe anytime with one click.

Own a Columbus business? 20,000+ page views in 30 days. Ads from $125/month. See ad options Follow Columbus Times on FacebookLocal news, events and people, in your feed every day. Follow

Comments

Be respectful. No personal attacks, hate speech, spam or anyone's private information. Every comment is reviewed before it appears. Comment rules

No comments yet. Be the first to share your thoughts.

Leave a comment

Replying to

Most read this week

  1. Columbus Weighs Truist Over Synovus and a Civic Center Manager
  2. County Line Road Interchange Plan: Comments Due Nov. 20
  3. Fort Benning Ceremony Calendar
  4. How to Ride METRA: $1.30 Fares, 10 Routes, Free Uptown Shuttle
  5. Columbus Bulk Trash, Limbs and Landfill Fees: What to Know