Audi's Middle Georgia Plant: $958 Million in Incentives, a Possible $3 Billion Second Phase With 3,000 More Jobs and an End-of-2033 Deadline
An Audi Q8 e-tron displayed at the IAA 2023 auto show in Germany. Photo: Alexander-93 / Wikimedia Commons (CC BY-SA 4.0)
COLUMBUS, Ga. - Documents obtained by the Atlanta Journal-Constitution show that Audi's planned plant in Middle Georgia could grow well beyond the $4 billion, 4,500-job project announced on Oct. 24. A possible second phase would add $3 billion in investment and 3,000 more jobs, if Audi chooses to pursue it, according to the newspaper's Nov. 2 report. The records also put the incentive package for phase one at no less than $958.4 million.
The plant is planned for the roughly 1,500-acre Middle Georgia Megasite near I-75 on the outskirts of Fort Valley, in Peach County. The project is in another part of the state from Columbus, but its size makes it a story for workers, suppliers and taxpayers across the state. The figures below are the newspaper's account of local records, and the project was not final when the report was published.
The numbers in the records
| Item | Phase one | Possible phase two |
|---|---|---|
| Investment | $4 billion | $3 billion more |
| Jobs | 4,500 | 3,000 more |
| Incentives | At least $958.4 million | A separate tax break worth about $361.1 million |
| Payment in lieu of taxes (PILOT) | About $295 million over 20 years, starting in 2028 | About $237.5 million over 20 years |
According to the AJC, the average salary is more than $63,000 a year, which works out to about $283 million in annual payroll at full employment, expected in 2031. Phase one and phase two together would total about $7 billion in investment and 7,500 jobs. The newspaper's headline referred to 6,000 jobs, a figure that does not match the phases it reports, so readers should rely on the phase-by-phase numbers.
What the incentive package includes
The AJC reported that the phase-one incentives include about $458.6 million in property tax savings over 20 years, a $94 million REBA grant and a $30 million EDGE grant. The state also provides free worker training, including a $73.5 million Quick Start Training Center. Clawbacks apply if Audi does not meet 80% of its investment and job promises, the newspaper reported.
For comparison, the AJC noted that Hyundai received $2.1 billion in incentives for a $7.6 billion project, and Rivian received a $1.5 billion package for a $5 billion factory. Those comparisons help show where the Audi package sits, though each deal has different terms and timelines. The comparison is the newspaper's, not a calculation by this site.
Timeline
- 2022: The state began assembling the megasite.
- Oct. 24, 2026: Phase one was announced at a campaign rally by President Donald Trump and Audi CEO Gernot Döllner, according to the AJC. Gov. Brian Kemp did not attend, but he and aides worked with Middle Georgia officials to close the deal.
- 2028: PILOT payments are scheduled to begin.
- 2031: Full employment is expected.
- End of 2033: Audi's deadline to exercise the phase-two expansion, after which terms would need to be renegotiated.
Questions that remain open
The documents the AJC obtained through an open records request to the Mid-Georgia Gateway Joint Development Authority were unsigned, the newspaper reported. The authority said local parties have signed all documents and that the terms have not changed, but it said finalization remains subject to approval by the State of Georgia and Audi of America. The Georgia Department of Economic Development called the project active, which allows records to be withheld under state law, and said Audi is completing its corporate approval process.
Audi's U.S. division declined to comment on confidential discussions or potential future investments, according to the AJC. Neither the authority nor the state said whether Audi would exercise the second phase. Those open points mean the totals above are a ceiling that depends on future decisions, not a commitment.
What it could mean for Columbus-area workers
The plant is planned in another part of the state, so any benefit for Columbus and Phenix City would come through hiring, training and suppliers rather than direct local incentives. The incentive package includes free worker training, including the Quick Start Training Center. Readers interested in jobs should watch announcements from the Georgia Department of Economic Development and the Mid-Georgia Gateway authority for hiring timelines, which the records do not provide.
Source: Atlanta Journal-Constitution, "Georgia Audi plant could get bigger" (Zachary Hansen, Nov. 2, 2026); Georgia Trend Daily (Nov. 2, 2026)
News organizations may republish this story with credit. See our guidelines.
Know someone who'd want to read this? Email it to a friend.
Plan your weekend with Columbus Times
Get This Weekend in Columbus every Thursday: the best local events, free things to do and family fun, plus each evening's local news. Free, and you can unsubscribe anytime.
By signing up you agree to get the Columbus Times email newsletter. Unsubscribe anytime with one click.
Comments
Be respectful. No personal attacks, hate speech, spam or anyone's private information. Every comment is reviewed before it appears. Comment rules
No comments yet. Be the first to share your thoughts.